Jokeri Light Rail contact lines installed in March
Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.
Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.
The contact line work is scheduled to last until Week 13.
Additional information
Text: Jokeri Light Rail
Read more news
Doctoral positions at Unite! universities now available in one place
Unite! students searching for doctoral positions can now explore a dedicated category in the Unite! Catalogue for Students.
Aalto University establishes Centre for Radical Creativity – aiming to support societal and corporate transformation
The centre responds to the interest and need for transformation among businesses and organizations and calls partners to join.